Date: February 2018 - ...
Project duration: ///
Location: Vandamme Lock / Zeebrugge
Division: K&C Diving
Project type: Underwater civil engineering, Port- and waterway infrastructure
At the beginning of 2018 Jan De Nul started a project that involved a complete renovation of door 4 of the Vandamme lock in Zeebrugge. K&C Diving provides all diving assistance during the entire project.
Below are some of the tasks we performed or are in progress:
- Diving assistance during work and removal of door 4
- Placing drying tray and closing caission
- Habitat works for restoring rails underwater
- Cleaning and sanding works of the lock gate, room and doorway
- Placing ballast baskets on lock bottom
- ...